Projects Requiring EIA: Government projects, Private projects
Abridged Assessments: Yes
Abridged Assessments Detail: There are provisions allowing for initial environmental examination (IEE) reports in Sri Lanka's legislative framework. According to the Central Environmental Authority, IEE reports are not required to be open for public comments. However, an IEE report shall be deemed to be a public document and shall open for inspection by the public.
Best Practices in Lieu of EIA: No
Who Conducts Screening: Government
Who Conducts Screening Detail: "The Minister shall determine. . . the activities in respect of which a licence is required to be obtained" under the Act. NE Act, sec. 23A(1) A consolidated list of the prescribed projects is maintained on the Central Environmental Authority's website: http://www.cea.lk/Prescribed_Projects.php
Criteria for Screening: List or appendix of project or activity types
Criteria for Screening Detail: Prescribed projects are listed in the EIA Regulations. A consolidated list of the prescribed projects is maintained on the Central Environmental Authority's website: http://www.cea.lk/Prescribed_Projects.php
Who Prepares EIA: Project Proponent (with or without contractor)
Who Prepares EIA Detail: Project approving agencies must require an initial environmental examination or an environmental impact assessment from any public or private body seeking approval for a project. NEA, sec. 23BB
Who Pays for EIA: Project Proponents
EIA Contractor Qualifications: No
EIA Contractor Qualifications Detail: Although the EIA law and regulations do not discuss contractor qualifications, the Central Environmental Authority maintains a list of EIA consultants. A project proponent is not required to use a listed consultant.
Conflict of Interest: No
Terms of Reference: Yes
Terms of Reference Detail: The project approving authority sets the terms of reference for an initial environmental examination report or EIA report, as the case may be. 1993 EIA Regulations (no internal numbering). The TOR must be conveyed to the project proponent within 30 days of receiving preliminary project information. Id.
Days for Decision Maker Review: 60+ days
Automatic Approval: No
Written Decision: Yes
Authority to Impose Conditions: Yes
Authority to Impose Conditions Detail: Every licence shall "be subject to such terms, conditions and such standards as may be prescribed." NE Act, sec. 23B
Expiry of Decision: 3 years
Expiry of Decision Detail: Every licence shall "be valid for such period as shall be specified in the licence, provided, it shall not be for more than a period of three years." NE Act. sec. 23B (as amended)
Financial Assurances or Bond: No