Projects Requiring EIA: Government projects, Private projects
Abridged Assessments: Yes
Abridged Assessments Detail: "B2" projects (moderate- low potential environmental impact) located inside an area with an approved zoning plan and "C" projects (low potential environmental impact) do not need to present a full EIA. The project developer submits a D2 form with information about the project and an Environmental Commitments Document. The D2 form includes a description of the proposed activity, including its potential to generate waste and emissions as well as other risks posed to the environment, and the proposed measures to mitigate such risks. EIA Regulations, Articles 9, 12 and 13
Best Practices in Lieu of EIA: No
Who Conducts Screening: Government
Who Conducts Screening Detail: The developer presents the project for an initial assessment proposing the category of its project. The government reviews the project's category and approves the developer's proposal. EIA Regulations, Article 8
Criteria for Screening: List or appendix of project or activity types, Proposed project or activity may cause significant environmental impact
Criteria for Screening Detail: EIA Regulations, Article 7
Who Prepares EIA: Project Proponent (with or without contractor)
Who Prepares EIA Detail: EIA Regulations, Article 112
Who Pays for EIA: Project Proponents
Who Pays for EIA Detail: The cost of environmental impact assessments shall be borne by the proponent. Law 7554, Art. 18. See also EIA Regulations, Art. 112.
EIA Contractor Qualifications: Yes
EIA Contractor Qualifications Detail: There is a registration process for environmental consultants in SETENA. Such process requires contractors to present relevant documentation about EIA-related training. EIA Regulations, Article 72
Conflict of Interest: Yes
Terms of Reference: Yes
Terms of Reference Detail: EIA Regulations, Articles 24, 27 & 28
Days for Decision Maker Review: 10 weeks (and up to 5 months for large-scale projects)
Automatic Approval: No
Written Decision: Yes
Written Decision Detail: The approval or denial of the activity, work or project shall be communicated by SETENA to the developer through an administrative, technical and legally motivated resolution. EIA Regulations, Art. 45
Authority to Impose Conditions: Yes
Authority to Impose Conditions Detail: EIA Regulations, Article 45
Expiry of Decision: 2 years
Expiry of Decision Detail: EIA Regulations, Article 46
Financial Assurances or Bond: Yes
Financial Assurances or Bond Detail: Organic Law of the Environment, Article 21; See also EIA Regulations, Articles 86, 87, and 88.