In 2016, an Administrative Law Judge recommended the Minnesota Public Utilities Commission (PUC) adopt the Federal Social Cost of Carbon (FSCC) established by the EPA should to determine the environmental cost values of burning coal in Minnesota. NOTE: This decision is only a recommendation that the PUC is not obligated to follow.
An association representing fisher people who would be impacted by a 4,150 MW coal-fired power plant planned for an Indian coast town filed a complaint with the International Finance Corporation (IFC) Compliance Advisor Ombudsman (CAO) raising concerns about IFC policy violations in the implementation of the project.
In its 2013 Audit and 2015 monitoring report, the CAO found several violations of IFC safeguard policies.
Among other findings, the CAO found that the IFC failed to ensure that consultation carried out as part of the environmental and social analysis constituted “effective consultation.” The CAO explained “[t]his lack of effective consultation with fishing communities early in the project cycle resulted in missed opportunities to assess, avoid and reduce potential adverse impacts of the project and to examine technically and financially feasible alternatives to the sources of adverse impacts[.]” In addition, the inadequate consultation and disclosure “hindered efforts to build and maintain over time a constructive relationship with project affected communities.”
In addition, the CAO found that the IFC’s environmental and social assessments “were not commensurate to risk,” failed to adequately review marine impact, and failed to adequately determine cumulative impacts.
The CAO also found the “IFC did not take the steps necessary to ensure that the application of [Performance Standard] 5 (Land Acquisition and Involuntary Resettlement) in relation to the complainants was properly assessed.”
Finally, the CAO determined that the IFC also failed to ensure World Bank Thermal Power Guidelines were applied properly.
The 2015 Report notes that the IFC has taken some steps to rectify problems raised in the Audit, but the CAO concludes that these steps are not “sufficient to address the findings of the audit at this stage.” Due to the continued violation of IFC policies, the CAO has kept the audit open for continued monitoring.
Chile's Supreme Court decided that the impacts of a coastal coal-fired power plant threatened the plaintiffs' and the larger fishing community's constitutional right to live in an environment free from contamination and ordered Endesa and government authorities to take measures necessary to protect marine species.
The Chilean Supreme Court revoked the environmental permits for the construction of Central Castilla, which would have been the largest proposed coal-fired power plant in South America. Project proponents submitted three separate EIAs for the power plant, a transmission line, and a port for coal imports. Applying the precautionary principle, the Supreme Court declared that the projects should be assessed together to determine the actual area of influence and cumulative impacts.
In the Matter of Application of Duke Energy Carolinas, LLC (Cliffside), Order Granting Certificate of Public Convenience and Necessity with Conditions, NC PUC, Docket No. E-7, Sub 790
The North Carolina Utilities Commission denied Duke Energy's request to build twin 800 MW coal-fired power plants, saying that the utility had failed to prove that both plants were needed to meet demand. (Duke Energy had planned to sell power from one of the plants). Instead, the state commission gave approval for one plant. The Commission also conditioned its approval on the utility’s commitment to retire older coal-fired generating facilities and to invest a small percentage of its annual retail electricity revenues on energy efficiency. Order E-70, Sub.790, p. 9.
The Oregon Public Utilities Commission (PUC) denied a request by Pacificorp to build two coal-fired electricity facilities to meet a projected increase in demand of 1,109 MW. The PUC determined in part that Pacificorp overestimated its resource needs and that the company failed to establish that constructing new electricity generating plants would best meet increased demand.
The Supreme Court of Montana found that the agency improperly relied on the federal land manager's findings about the impact of a proposed coal-fired power plant. The law required the agency to make an independent inquiry.
The failure of the Minister of International Trade and Industry to exercise the authority to implement safety regulations immediately after the enactment of the Pneumoconiosis Law is illegal for the purpose of the Law Concerning State Liability for Compensation. The period of extinctive prescription shall start from the time when all or part of damage has arisen from an unlawful act if the damage, due to its nature, arises after a considerable period of time has passed since the termination of the act of causing the damage.
A local environmental association (“Save the Vaal Environment”) petitioned South Africa’s mining authority to comment on an application by Sasol Mining for a license to mine coal near the Vaal River, but the mining authority refused to provide such an opportunity and issued the mining license to Sasol Mining, so Save the Vaal Environment sought judicial review of the mining authority's decision. The Supreme Court of Appeal agreed with Save the Vaal Environment that the mining authority should have applied the audi alteram partem rule (or “audi-rule”) to provide an opportunity for comment.