The National Green Tribunal ordered coal mining and energy companies to implement a series of measures to reduce environmental pollution and health impacts associated with their facilities operating in the Tamnar and Charghoda coal blocks in the state of Chhattisgarh. The Tribunal declared that no expansion of mining or industrial activities in the area could be approved until a thorough environmental carrying capacity study is completed.
The Madras High Court determined that the operator of a coal-fired power plant isn't beneficially utilizing fly ash, among other regulatory violations. Thus, the court enjoined the operator from dumping material that would affect the marsh land in Vallur Village, Tamil Nadu.
An association representing fisher people who would be impacted by a 4,150 MW coal-fired power plant planned for an Indian coast town filed a complaint with the International Finance Corporation (IFC) Compliance Advisor Ombudsman (CAO) raising concerns about IFC policy violations in the implementation of the project.
In its 2013 Audit and 2015 monitoring report, the CAO found several violations of IFC safeguard policies.
Among other findings, the CAO found that the IFC failed to ensure that consultation carried out as part of the environmental and social analysis constituted “effective consultation.” The CAO explained “[t]his lack of effective consultation with fishing communities early in the project cycle resulted in missed opportunities to assess, avoid and reduce potential adverse impacts of the project and to examine technically and financially feasible alternatives to the sources of adverse impacts[.]” In addition, the inadequate consultation and disclosure “hindered efforts to build and maintain over time a constructive relationship with project affected communities.”
In addition, the CAO found that the IFC’s environmental and social assessments “were not commensurate to risk,” failed to adequately review marine impact, and failed to adequately determine cumulative impacts.
The CAO also found the “IFC did not take the steps necessary to ensure that the application of [Performance Standard] 5 (Land Acquisition and Involuntary Resettlement) in relation to the complainants was properly assessed.”
Finally, the CAO determined that the IFC also failed to ensure World Bank Thermal Power Guidelines were applied properly.
The 2015 Report notes that the IFC has taken some steps to rectify problems raised in the Audit, but the CAO concludes that these steps are not “sufficient to address the findings of the audit at this stage.” Due to the continued violation of IFC policies, the CAO has kept the audit open for continued monitoring.
Tribunal quashed the environmental clearance issued for a coal-fired power plant for failure to prepare an adequate cumulative impact assessment. “Rapid” assessment submitted by power company did not provide a comprehensive view of the impacts.
National Green Tribunal overturned an environmental clearance issued for a coal-fired power plant proposed by India’s largest thermal power producer. The Tribunal found that environmental information had been concealed and misrepresented, and the EIA and public participation processes were faulty.
Environment minister improperly rejected advice from an expert committee recommending that large-scale coal mining proposal in a forest area not proceed. Although the committee’s advice is not binding on the Minister, it nevertheless cannot be ignored without credible scientific basis.
This project has been made possible by the generous
support of the Philip Stoddard Brown and Adele Smith Brown Foundation