The High Court of Kenya remanded the environmental license issued for a port project for reconsideration and directed the project proponent to pay Kshs. 1.7 billion in compensation to affected fishing communities who will be impacted by the project. During the reconsideration process, decisionmakers must evaluate the external costs of the port project on the environment and local communities.
In 2016, an Administrative Law Judge recommended the Minnesota Public Utilities Commission (PUC) adopt the Federal Social Cost of Carbon (FSCC) established by the EPA should to determine the environmental cost values of burning coal in Minnesota. NOTE: This decision is only a recommendation that the PUC is not obligated to follow.
Environment minister improperly rejected advice from an expert committee recommending that large-scale coal mining proposal in a forest area not proceed. Although the committee’s advice is not binding on the Minister, it nevertheless cannot be ignored without credible scientific basis.
Upholding Land and Environment Court decision declaring that an open-cut coal mine should not be allowed to expand because the economic benefits of continued mining do not outweigh the impacts to nearby residents and loss of biodiversity.
The Land and Environment Court of NSW decided that the proposed mine expansion project would cause unacceptable environmental and social impacts, which were not adequately evaluated in the economic assessments, and that the approval conditions would not satisfactorily offset such impacts, so it decided to refuse Warkworth’s expansion project proposal and replace the administrative decision with its refusal.